The Town of Milton will begin roadway reconstruction on Hillside Street andย Forest Street commencing Monday, June 13th, 2016 at 7:00 a.m.
Construction will begin by pulverizing and grading the existing roadway onย Monday June 13th through Thursday June 16th. A binder course of asphaltย will be applied to the pulverized roadway later next week. The top layer ofย asphalt will be paved later this summer.
The roadways will remain open to at least one-way traffic at all times,ย and access will always be available for residents. Street parking will beย prohibited during roadway construction, 7am to 5pm. Police details willย be onsite to direct local traffic and assist the construction crews. If you haveย any questions or concerns, please call the Department of Public Works โย Engineering at (617) 898-4900.